_CASE STUDY 2
The owners of this Waipu Cove section wanted to build as close to the view as
possible so they called PoleSpecs to ensure a solid foundation for their investment.
Sam Cumming from PoleSpecs says the cliff needed to be pinned. "We had to
drill 17 11-metre deep holes, which we lined with steel cages and then poured
concrete into. We used pendulum excavator mounters for easy site access to drill
the holes," he said.
One of the challenges the PoleSpecs team faced was boulders in the cliff. "While
the engineers had done a geological report, the reports are never foolproof and
we did encounter several large rocks, as well as the bedrock at a depth of about
8m. Having the right equipment ensured a successful outcome," says Sam.
|
|
|
 |